The EXIN PR2F (PRINCE2 Foundation written) Exam is an important certification for individuals who wish to acquire a fundamental understanding of project management using the PRINCE2 methodology. PRINCE2 7 Foundation written Exam certification is internationally recognized and is available in several languages, making it accessible to professionals across different regions. By passing the exam, candidates demonstrate their commitment to improving their knowledge and skills in project management, which boosts their job prospects and promotes their professional development.


To pass the PRINCE2 Foundation Exam, candidates must demonstrate their ability to apply PRINCE2 principles to real-world scenarios. PRINCE2Foundation exam covers a wide range of topics, including project management terminology, the PRINCE2 framework, the seven principles of PRINCE2, the seven themes of PRINCE2, the seven processes of PRINCE2, and the tailoring of PRINCE2 to suit different project environments. The PRINCE2 Foundation Exam is an excellent starting point for individuals who want to pursue a career in project management or enhance their project management skills.

 

NEW QUESTION # 29
Which is an objective of the Initiating a Project process?

  • A. Develop the corporate quality management system as part of the Project Initiation Documentation
  • B. Summarize how the organization's project management method will be tailored for the project
  • C. Prepare the plans for the subsequent stages
  • D. Request authority from corporate management to deliver the project

Answer: B


NEW QUESTION # 30
Which is a purpose of the change theme?

  • A. To prevent change to baselined products
  • B. To assess and control uncertainty
  • C. To establish mechanisms to monitor and compare actual achievements against those planned
  • D. To identify, assess and control any potential and approved changes to baselined products

Answer: D

Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-prince2-change- theme


NEW QUESTION # 31
Which describes an off-specification?

  • A. A prototype demonstrating a possible design solution
  • B. The production of more than the defined quantity of a specialist product
  • C. The addition of an improvement to a product description
  • D. An interdependency between products that was previously unidentified

Answer: D

Explanation:
Explanation
Reference https://www.prince2primer.com/prince2-change-control/


NEW QUESTION # 32
Identify the missing words in the following sentence.
At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

  • A. Quality Management Strategy
  • B. Communication Management Strategy
  • C. Follow-on action recommendations
  • D. Stage Plan

Answer: B


NEW QUESTION # 33
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

  • A. Project Initiation Documentation
  • B. Benefits Review Plan
  • C. Project mandate
  • D. Project Brief

Answer: A


NEW QUESTION # 34
Which describes an off-specification?

  • A. A prototype demonstrating a possible design solution
  • B. The production of more than the defined quantity of a specialist product
  • C. The addition of an improvement to a product description
  • D. An interdependency between products that was previously unidentified

Answer: D

Explanation:
Reference https://www.prince2primer.com/prince2-change-control/


NEW QUESTION # 35
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

  • A. Principles
  • B. Techniques
  • C. Themes
  • D. Processes

Answer: A


NEW QUESTION # 36
Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.

  • A. Plan
  • B. Stakeholder interests
  • C. Management strategies
  • D. Time-driven controls

Answer: A


NEW QUESTION # 37
Which is a purpose of an Issue Report?

  • A. Provide the status of all issues in a Work Package
  • B. Notify the Project Manager of all new issues in a Work Package
  • C. Document an issue that needs to be handled formally
  • D. Provide the status of all the issues in a stage

Answer: C


NEW QUESTION # 38
What is an advantage of dividing the project into stages?

  • A. The project can be authorized by the project manager on a stage by stage basis
  • B. Detailed plans can be prepared closer to the time events will take place
  • C. the project board can delegate management of the project to team managers
  • D. The project brief can be updated towards the end of each stage

Answer: B

Explanation:
One of the advantages of dividing the project into stages, as advocated by PRINCE2, is that detailed plans can be prepared closer to the time events will take place. This allows planning to be based on more accurate, up-to-date information, improving the relevance and accuracy of the plans. This approach also allows for better response to changes and risks, as planning for later stages can adjust based on the outcomes and learnings from earlier stages.References: PRINCE2 Foundation Manual


NEW QUESTION # 39
Which is a benefit of using PRINCE2?

  • A. It promotes consistency of project work and the ability to reuse project assets.
  • B. It enables a project manager to be accountable for the success of a project
  • C. It includes techniques for critical path analysis and earned value analysis
  • D. It prevents any changes once the scope of a project has been agreed

Answer: A

Explanation:
Section: Volume B


NEW QUESTION # 40
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

  • A. Corporate group
  • B. Executive
  • C. Project Board
  • D. Project Assurance

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:


NEW QUESTION # 41
Which process provides information for the project board to review a completed stage and confirm continued business justification?

  • A. Closing a project
  • B. Managing a stage boundary
  • C. Directing a project
  • D. Controlling a stage

Answer: B

Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2.com/uk/prince2-processes


NEW QUESTION # 42
Why is the 'learn from experience' principle applied to a project?

  • A. To enable the project team to repeat successes from previous projects
  • B. To enable the project team to develop a business case for the project
  • C. To allow the project to be divided into management stages
  • D. To enable the project team to use tolerances to delegate authority

Answer: A

Explanation:
Explanation
Reference https://link.springer.com/chapter/10.1007/978-3-319-23000-9_4


NEW QUESTION # 43
Which is a purpose of a quality register?

  • A. To record cross-references to issues relating to the quality of the products
  • B. To capture quality concerns about completed products
  • C. To record the date a completed work package was received
  • D. To provide the status of quality activities carried out for completed products

Answer: C

Explanation:
Section: Volume B


NEW QUESTION # 44
Which process provides information for the project board to review a completed stage and confirm continued business justification?

  • A. Closing a project
  • B. Managing a stage boundary
  • C. Directing a project
  • D. Controlling a stage

Answer: B

Explanation:
Reference https://www.prince2.com/uk/prince2-processes


NEW QUESTION # 45
Which is a purpose of the Quality theme?

  • A. Establish how the project will ensure that all products created meet their requirements
  • B. Identify all the products of the project to ensure the scope has been adequately defined
  • C. Determine the communication needs of the organization's quality assurance function
  • D. Establish quality assurance to maintain the quality management system

Answer: A


NEW QUESTION # 46
Which is a minimum requirement for applying the business case theme?

  • A. To define the actions required to confirm the project's benefits are realized
  • B. To monitor changes to the project plan to identify exceptions
  • C. To report on project performance at project closure
  • D. To provide statements of actual benefits at benefits reviews

Answer: B

Explanation:
Explanation
Reference https://www.whatisprince2.net/prince2-theme-business-case.php


NEW QUESTION # 47
......


How much PRINCE2-Foundation: PRINCE2 Foundation Exam Cost

The PRINCE2 Foundation accreditation expired after three years. You may either retake a PRINCE2 Foundation Exam before the expiry date or maintain your certification using CPD points and digital badges to ensure that your Foundation status does not have defects. If you choose for CPD travel, you have to buy MY PRINCE2 membership that costs £85 + VAT a year.

 