Pass The Open Group OG0-093 Exam Info and Free Practice Test
New 2022 Latest Questions OG0-093 Dumps - Use Updated The Open Group Exam
Exam Details
The OG0-093 test includes two sections as it is a combination of the Part 1 (0G0-091) and the Part 2 (OG0-092) exams. Part 1 has 40 multiple-choice questions and lasts for 60 minutes. The passing score is 55%. Part 2 includes 8 complex scenario-based questions and has the time duration of 90 minutes. The pass mark is 60%. Both these tests will cost you $550. The candidates can take them in English or Simplified Chinese.
To get the TOGAF 9 Certified certification, the students must meet the requirements for each section of the exam. If you miss the minimum requisite score in any of the sections, you have to wait for one month to try it again. Please note that once you have completed the first part and moved to the second one, it will not be possible to come back to the questions in the first part.
NEW QUESTION 55
Which of the following best describes the purpose of the Architecture Requirements Specification?
- A. It contains an assessment of the current architecture requirements
- B. It provides a set of statements that outline what a project must do to comply with the architecture
- C. It defines the scope and approach to complete an architecture project
- D. It is sent from the sponsor and triggers the start of an architecture development cycle
- E. It provides a list of work packages and a schedule for implementation of the target architecture.
Answer: B
Explanation:
Section: Part 1
Explanation/Reference: http://pubs.opengroup.org/architecture/togaf91-doc/arch/chap36.html#tag_36_02_06
NEW QUESTION 56
Which one of the following statements about the Requirements Management phase is true?
- A. All requirements fed into the phase are prioritized, and those of low priority are deferred until the next iteration of the ADM cycle
- B. The phase manages the flow of requirements, storing them, and feeding them in and out of the relevant ADM phases
- C. The phase operates like a waiting room, and all requirements fed in to the phase must be resolved by the end of the current ADM cycle
- D. The phase resolves the requirements that are fed into it from the other ADM phases
- E. The phase generates the requirements for a given ADM cycle using the Business Scenario technique
Answer: B
NEW QUESTION 57
In Phase G, what document establishes the connection between the architecture organization and the implementation organization?
- A. Transition Architecture
- B. Requirements Impact Statement
- C. Architecture Landscape
- D. Architecture Contract
- E. Architecture Roadmap
Answer: D
Explanation:
Section: Part 2
Explanation
NEW QUESTION 58
Which of the following best describes the purpose of the Architecture Definition Document?
- A. To show progression of change from the Baseline Architecture to the Target Architecture
- B. To provide a high-level view of the end architecture product
- C. To ensure that architecture information is communicated to the right stakeholders at the right time
- D. To govern the architecture throughout its implementation process
- E. To act as a deliverable container for artifacts created during a project
Answer: E
Explanation:
Section: Part 2
Explanation/Reference:
Reference https://pubs.opengroup.org/architecture/togaf91-doc/arch/chap36.html
NEW QUESTION 59
Scenario
Please read this scenario prior to answering the Question
Your role is that of Lead Enterprise Architect within the staff headquarters of a large hotel chain. The chain manages over 500 hotels across North America and Canada, with another 230 hotels internationally in the United Kingdom, Europe, Australia and New Zealand. Unlike other hotel chains, which are often a mix of company-owned and franchised units, each hotel in the chain is an independently owned and operated franchise. Many of the hotels use the same internal IT systems that they used before they joined the franchise. Until recently, the only requirement that has been placed on each hotel is that they use a standard financial reporting system to report their financial results to the headquarters on a weekly basis.
The CEO of the chain has stated his concerns about the inefficiencies of the current approach and identified the need to change. He has defined a new strategic vision that will enhance the business by providing its franchisees new support services including worldwide reservations, global, national and regional marketing as well as consolidated financial, logistics, and yield management. This strategy is part of the long-term commitment to enhance the brand image and drive superior revenue for the chain. He has also stated that he expects improved financial results by the end of the current fiscal year.
These changes will provide the chain with improved utilization of its capacity and more efficient operations.
The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising into key national and regional markets to improve yields.
The chain has a mature enterprise architecture practice based in its headquarters and uses TOGAF 9 as the method and guiding framework. The CIO is the sponsor of the activity.
In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire chain, including detailed requirements and recommendations.
Based on the recommendations from the initial study, the chain has taken the decision to adopt a packaged suite of integrated applications that is tailored to the needs of the hospitality industry.
Refer to the scenario
You have been asked by the Chief Architect to propose the best approach for architecture development to realize the CEO's vision.
Based on TOGAF, which of the following is the best answer?
- A. You propose that the team focus on architecture definition, with a specific emphasis on understanding the strategic change parameters of the business strategy. Once understood, the team will be in the best position to identify the requirements, drivers, issues, and constraints for this engagement. You would ensure that the target architecture addresses non-functional requirements so as to ensure the target architecture is robust and secure.
- B. You propose that this engagement define the baseline Technology Architecture first in order to assess the current infrastructure capacity and capability. Then the focus should be on transition planning and architecture deployment. This will identify requirements to ensure that the projects are sequenced in an optimal fashion so as to realize the vision.
- C. You propose that the target architecture is defined first, followed by transition planning. This is because the vision is well understood and the strategic architecture agreed. The target first approach will ensure that the current problems and inefficiencies of the baseline architecture are not carried forward, and that the proposed solution addresses the requirements identified in the initial study.
- D. You propose that the team focus on defining the target architecture by going through the architecture definition phases (B-D). This is because the initial study identified the need to change. This will ensure that the change can be defined in a structured manner and address the requirements needed to realize the vision.
Answer: C
NEW QUESTION 60
What does the TOGAF standard provide to guide architectural activity within the enterprise in terms of structures, roles, responsibilities, and processes?
- A. Enterprise Continuum
- B. Architecture Development Method
- C. Architecture Content Framework
- D. Architecture Capability Framework
Answer: A
Explanation:
Explanation/Reference:
Reference: https://pubs.opengroup.org/architecture/togaf91-doc/arch/
NEW QUESTION 61
Which one of the following best describes the purpose of the Communications Plan?
- A. To show progression of change from the Baseline Architecture to the Target Architecture
- B. To act as a deliverable container for artifacts created during a project
- C. To ensure that information is communicated to the right stakeholders at the right time
- D. To inform the Architecture Board of changes to the architecture
- E. To ensure that the results of a Compliance Assessment are distributed to the Architecture Board
Answer: C
NEW QUESTION 62
Which of the following describes a purpose of an Architecture Compliance review?
- A. Identifying work packages for inclusion in the Architecture Roadmap
- B. Identifying stakeholders and their concerns
- C. Identifying the business transformation risks for an architecture project
- D. Identifying criteria for procurement activities
- E. Identifying relationships between management frameworks
Answer: D
Explanation:
Reference:http://pubs.opengroup.org/architecture/togaf9-doc/arch/chap48.html#tag_48_03
NEW QUESTION 63
Which section of the TOGAF template for Architecture Principles should describe situations where one principle would be given precedence over another?
- A. Trade-oils
- B. Name
- C. Implications
- D. Statement
- E. Rationale
Answer: E
Explanation:
Section: Part 1
NEW QUESTION 64
Complete the sentence. TOGAF covers the development of four architecture domains, Business, Data, Technology and ___________.
- A. Vision
- B. Application
- C. Capability
- D. Segment
- E. Transition
Answer: B
NEW QUESTION 65
Which of the following is a responsibility of an Architecture Board?
- A. Creating the Statement of Architecture Work
- B. Establishing targets for re-use of components
- C. Conducting assessments of the maturity level of architecture discipline within the organization
- D. Identifying the Lead Enterprise Architect to manage an architecture compliance review
- E. Allocating resources for architecture projects
Answer: C
NEW QUESTION 66
In which Phase of the ADM does the business scenario technique figure most prominently?
- A. Technology Architecture
- B. Preliminary
- C. Information Systems Architectures
- D. Business Architecture
- E. Architecture Vision
Answer: E
NEW QUESTION 67
Which of the following describes a purpose of an Architecture Compliance review?
- A. Identifying where standards may require modification
- B. Identifying business transformation risks for an architecture project
- C. Identifying stakeholders and their concerns
- D. Identifying relationships between management frameworks
Answer: A
Explanation:
Explanation/Reference:
Reference: http://pubs.opengroup.org/architecture/togaf8-doc/arch/chap24.html
NEW QUESTION 68
TOGAF Part VII, Architecture Capability Framework recommends use of an ADM cycle for establishing an architecture practice. In this scenario which architecture would describe the organizational structure for the architecture practice?
- A. Transition Architecture
- B. Business Architecture
- C. Technology Architecture
- D. Application Architecture
- E. Data Architecture
Answer: B
Explanation:
Section: Part 1
NEW QUESTION 69
Scenario: Intrepid Space Industries
Please read this scenario prior to answering the question
Intrepid Space Industries is the prime contractor for the Telesto Unmanned Spacecraft program. Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. Intrepid is moving aggressively to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.
To achieve this goal, Intrepid needs to define Baseline and Target Architectures. These architectures must address key stakeholders' concerns such as:
1.What groups of people should be involved in procurement-related business processes?
2.What current applications do those groups use?
3.Which procurement-related business processes are supported by zero, one, or many existing applications?
4.What are the overall lifetimes of the Request for Proposal and Purchase Order business objects? What non-procurement applications will need to be integrated with any new procurement applications?
5.What data will need to be shared?
At present, there are no particularly useful architectural assets related to this initiative, so all assets need to be acquired and customized or created from scratch. The company prefers to implement existing package applications from systems vendors with little customization.
The architecture development project has just completed its Architecture Context iteration cycle and is about to begin the Architecture Definition iteration cycle. Intrepid is using TOGAF for its internal Enterprise Architecture activities. It uses an iterative approach for executing Architecture Development Method (ADM) projects.
The architecture development project has just completed its Architecture Context iteration cycle and is about to begin the Architecture Definition iteration cycle.
Refer to the Intrepid Space Industries Scenario.
You are serving as the Lead Architect.
You have been asked to identify the most appropriate architecture viewpoints for this situation.
Based on TOGAF 9, which of the following is the best answer?
- A. In the early iterations of the Architecture Definition: Describe the Baseline Business Architecture with a Baseline Business Process catalog Describe the Baseline Application Architecture with a Technology Portfolio catalog Describe the Baseline Data Architecture with a Data diagram In the later iterations of the Architecture Definition: Describe the Target Business Architecture with an Actor/Process/Data catalog Describe the Target Application Architecture with a System/Technology matrix Describe the Target Data Architecture with a Data Dissemination diagram
- B. In the early iterations of the Architecture Definition: Describe the Baseline Business Architecture with an Organization/Actor catalog Describe the Baseline Application Architecture with a System/Function matrix Describe the Baseline Data Architecture using a Data Entity/Data Component catalog In the later iterations of the Architecture Definition: Describe the Target Business Architecture with an Organization/Actor catalog Describe the Target Application Architecture using Application Communication diagrams and an Application Interaction matrix Describe the Target Data Architecture with a System/Data matrix
- C. In the early iterations of the Architecture Definition: Describe the Target Business Architecture with a Business Service/Function catalog and a Business Interaction matrix Describe the key business objects with Product Lifecycle diagrams Describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix Describe the Target Data Architecture with a Data Entity/business Function matrix and a System/Data matrix In the later iterations of the Architecture Definition: Describe the Baseline Business Architecture with a Business Service/Function catalog and a Business Interaction matrix Describe the Baseline Application Architecture with a System/Organization matrix and a System/function matrix Describe the Baseline Data Architecture with a Data Entity/Data Component catalog
- D. In the early iterations of the Architecture Definition: Describe the Target Business Architecture with a Business Service/Function catalog and an Organization/Actor catalog Describe the key business objects with Data Lifecycle diagrams Describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix Describe the Target Data Architecture with a System/Data matrix In the later iterations of the Architecture Definition: Describe the Baseline Business Architecture with a Business Service/Function catalog and a Business Interaction matrix Describe the Baseline Application Architecture with an Application and User Location diagram and a System/Function matrix Describe the Baseline Data Architecture with a Data Entity/Data Component catalog
Answer: D
NEW QUESTION 70
In which phase of the ADM cycle do building blocks become implementation-specific?
- A. Technology Architecture
- B. Opportunities and Solutions
- C. Architecture Vision
- D. Data Architecture
- E. Business Architecture
Answer: B
Explanation:
Explanation/Reference:
Reference: http://www.ict.griffith.edu.au/~bernus/taskforce/archive/togaf/togaf4/section4.htm
NEW QUESTION 71
Which of the following TOGAF components was created to enable architects to design architectures addressing Boundaryless Information Flow?
- A. The Integrated Information Infrastructure Model
- B. The Architecture Repository
- C. The Enterprise Continuum
- D. The TOGAF Technical Reference Model
Answer: A
NEW QUESTION 72
Complete the sentence. A set of architecture principles that cover every situation perceived throughout the enterprise meet the recommended criteria of__________.
- A. robustness
- B. stability
- C. consistency
- D. understandability
- E. completeness
Answer: E
NEW QUESTION 73
Complete the sentence. There are five criteria that distinguish a good set of principles: Understandable, Robust, Complete, Consistent and __________.
- A. Comprehensive
- B. Dynamic
- C. Stable
- D. Rational
- E. Agile
Answer: C
NEW QUESTION 74
Which section of the TOGAF document contains a structured metamodel for architectural artifacts?
- A. Part II: Architecture Development Method
- B. Part III: ADM Guidelines and Techniques
- C. Part IV: Architecture Content Framework
- D. Part VI: TOGAF Reference Models
- E. Part VII: Architecture Capability Framework
Answer: C
Explanation:
Section: Part 1
NEW QUESTION 75
Which one of the following is an objective of the Preliminary Phase of the ADM?
- A. To prioritize work packages
- B. To develop a Target Business Architecture
- C. To define the architecture principles
- D. To define, scope and prioritize architecture tasks
- E. To obtain management commitment for this cycle of the ADM
Answer: C
Explanation:
Section: Part 2
NEW QUESTION 76
Which of the following does the TOGAF document define as architectural work product that describes an aspect of the architecture?
- A. Framework
- B. Application Platform Interface
- C. Deliverable
- D. Artifact
- E. Building Block
Answer: D
NEW QUESTION 77
Which of the following best describes the purpose of the Architecture Vision?
- A. It contains an assessment of the current architecture requirements
- B. It provides a schedule for implementation of the target architecture
- C. It defines the scope and approach to complete an architecture project
- D. It is sent from the sponsor and triggers the start of an architecture development cycle
- E. It provides a high-level aspirational view of the end architecture project
Answer: E
NEW QUESTION 78
Complete the sentence. The TOGAF standard covers the development of four architecture domains.
Application, Data, _________________.
- A. Capability and Segment
- B. Business and Technology
- C. Vision and Requirements
- D. Information and Knowledge
- E. Baseline and Transition
Answer: B
Explanation:
Explanation
Reference https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap06.html
NEW QUESTION 79
Scenario: Mobile Telco
Please read this scenario prior to answering the Question.
Mobile Telco is a mobile telecommunications company formed through a series of mergers and acquisitions. They are yet to fully integrate the customer service systems for the most recent acquisitions, and as result, customer service has been a major concern for the Chief Technology Officer. Results for the last two quarters have shown that Average Revenue Per User (ARPU) and the customer retention (Churn) rate have fallen below the industry average.
The Corporate Marketing group has published some new findings about customer satisfaction. The customers appear to be switching to AirLight, a competitor, because of superior customer service. Mobile Telco actually has better coverage in nearly all markets than AirLight, and good roaming agreements that keep rates low for business travelers. But, customer satisfaction has remained low. The Business Strategy group and the Enterprise Architecture group have conducted a high-level project to develop the enterprise- wide strategic plan.
They have developed a business scenario which contains a good conceptual model of what needs to be done, and also identifies the key requirements. This was used in preparing the proposal presented to the Executive Council and the Corporate Board. The planning for the program has been underway for several months. Mobile Telco has selected TOGAF 9 as the basis for its Enterprise Architecture. The Corporate Board has approved funding for a multi-million Euro conversion to transition to a packaged Customer Service System. It is anticipated that the overall program will take five years to complete, but there are some tactical projects that can commence immediately to address the situation.
The Executive Council has stated that the program should define specific initiatives to enable each regional business unit to create an implementation of the Customer Service System. The implementation must meet the needs of the business unit and still provide the information needed to enable major improvements to the customer.
Refer to the Mobile Telco Scenario
You are serving as the Lead Architect for the Performance and Integrity project of the Customer Service System program.
The project has been chartered to address the architecture(s) required to support the Customer Service System from an infrastructure perspective. At the present time, the project team is conducting an architecture development project that is focused on the customer self-service capability, which was defined as part of the earlier strategic planning activities. This capability will enable customers to access their accounts, pay bills, request account reviews, and provision services from any web-enabled device.
The project team has gathered information about the self-service capability, developed a business scenario, and used the results to define an Architecture Vision for achieving the capability.
You have been asked to recommend the course of action to complete the project.
Based on TOGAF 9, which of the following is the best answer?
- A. The remaining architecture definition work should be focused en mapping out the technology and infrastructure capability in the Technology domain. In Phases E and F, the capability should be broken down into a set of Solution Building Blocks that will be implemented to realize the Target Architecture.
The Solution Building Blocks will provide the basis for the completed Architecture Definition Document that will be submitted for approval. Upon approval, the implementation team will conduct Compliance Assessments to ensure that the self-service capability is compliant with the overall Enterprise Architecture. - B. In the remaining architecture definition phases, the project team should map out the capability across the Business, Information Systems, and Technology domains. In Phases E and F, the capability should be broken down into a set of increments that are sequenced into Transition Architectures that will lead to the realization of the Target Architecture.
The resulting Solution Building Blocks will then provide the basis for the capability increment solutions.
The completed Architecture Definition Document and the implementation end Migration Plan will be submitted for approval. Upon approval, the architecture team will oversee the implementation process through monitoring Architecture Contracts and by conducting Compliance Assessments. - C. In the remaining architecture definition phases, the project team should map out the capability across the Business, Information Systems, and Technology domains. In Ftiases E and F, the capability should be broken down into a set of increments that define the Target Architecture. The resulting Solution Building Blocks will provide the basis for tne capability increment solutions. The completed Architecture Definition Document and the Implementation and Migration Plan will be submitted for approval. Upon approval, the architecture team will oversee the implementation process through monitoring Architecture Contracts and by conducting Compliance Assessments.
- D. In the remaining architecture definition phases, the project team should map out the capability in the Technology domain. In Phases E and F, the capability should be broken down into a set of Solution Building Blocks that define the Target Architecture. Where possible, the Solution Building Blocks should be drawn from the Architecture Repository.
The completed Architecture Definition Document and the Implementation and Migration Plan will be submitted for approval. Upon approval, the architecture team will conduct Compliance Assessments to ensure that the Target Architecture is properly implemented.
Answer: A
NEW QUESTION 80
......
The Open Group OG0-093 Exam
This exam validates the candidate ability to understanding of the ArchiMate specification and support the ArchiMate modeling language. It also assessment both of the course and the personnel and organization.
Latest OG0-093 Exam Dumps The Open Group Exam: https://www.practicedump.com/OG0-093_actualtests.html
Pass The Open Group OG0-093 PDF Dumps Recently Updated 365 Questions: https://drive.google.com/open?id=1Ef-fwTY3HDPwKh251pE188IkpqVnUkSN