NEW QUESTION 14
For your project, you create a new planning area and consider how to create analytics and alerts for it.How can you create these objects?
- A. Create analytics and alerts in the new planning area from scratch using the Intelligent Visibility application.
- B. Use the option for copying analytics and alerts when creating a new planning area from the sample SAPIBP1.
- C. Merge analytics and alerts into a new planning area from any sample planning area.
- D. Use the option for copying analytics and alerts into the new planning area from the existing custom planning area.
Answer: B
NEW QUESTION 15
Which of the following are functions of SAP IBP for demand?Note: There are 2 correct answers to this question.
- A. Detailed statistical analysis of demand data using predictive analytics tools
- B. Consideration of demand-driven analysis for buffer positioning.
- C. Demand sensing of demand data using predictive analytics tools
- D. Embedded, on-the-fly demand analytics
Answer: A,D
NEW QUESTION 16
What are the possible ways that an attribute intended for use as an attribute as a key figure can be created and assigned?
- A. Created as type NVARCHAR and assigned to an external master data type
- B. Created as type INTEGER and assigned to a simple master data type
- C. Created as type INTEGER and assigned to a compound master data type
- D. Created as type DECIMAL and assigned to a compound master data type
Answer: D
NEW QUESTION 17
What does ABC/XYZ segmentation allow you to do?Note: There are 2 correct answers to this question.
- A. Use forecasting algorithms that are specific to seasonal demands of SKUs in the segment "B".
- B. Identify inventory items that require closer attention.
- C. Choose time-independent key figures as segmentation measures.
- D. Substitute missing values in case of sporadic demands.
Answer: B,C
NEW QUESTION 18
What is a prerequisite for modeling outsourced manufacturers with production capacity using the Supply Optimizer?
- A. Model relative production costs across internal locations and outsourced manufacturing locations
- B. Ensure that the outsourced manufacturing locations have a separate subnetwork
- C. Model target inventory and stocks at the outsourced manufacturing location
- D. Use production lead times and offsets to manage components at the outsourced manufacturing location
Answer: A
NEW QUESTION 19
What function would you use to configure a year-to-date calculation?
- A. Rolling Aggregation
- B. Dynamic Rolling Aggregation
- C. Cumulative Aggregation
- D. Last Period Aggregation
Answer: C
NEW QUESTION 20
What do you need to be aware of when using multiple pairs of key figures in one copy operator? Note: There are 2 correct answers to this question.
- A. Copying multiple key figures on different planning levels is not possible.
- B. Copying multiple key figures can be processed sequentially.
- C. If necessary source key figures values are disaggregated.
- D. If necessary target key figures values are disaggregated.
Answer: B,C
NEW QUESTION 21
Which of the following approaches could you take to reduce run times of an optimizer?Note: There are 3 correct answers to this question.
- A. Keep the number of fairshare segments small.
- B. Split into multiple planning areas to support weekly vs. daily planning needs.
- C. Avoid using telescopic time buckets.
- D. Increase the use of incremental lot size beyond the frozen horizon.
- E. Use non-overlapping networks by using subnetwork ID maintained at Location-Products to reduce the size of the problem.
Answer: B,C,E
NEW QUESTION 22
You are working to realign the data due to a recent warehouse closure.What should you be aware of in regards to the realignment steps settings?Note: There are 2 correct answers to this question.
- A. The number of steps in the realignment run is limited to 255.
- B. The name of the realignment step should be no longer than 20 characters.
- C. A realignment step can change master data, planning objects and key figures.
- D. You must mark the realignment step as "shared" and assign the steps to users.
Answer: C,D
NEW QUESTION 23
Which constraints are taken into account by the Time-Series-Based Supply Planning Heuristic (Infinite)?Note: There are 3 correct answers to this question.
- A. Transportation lead times
- B. Maximum lot size
- C. Minimum lot size
- D. Aggregated constraints
- E. Adjusted transport receipts
Answer: A,B,E
NEW QUESTION 24
You created a key figure and want to add calculations.Which of the following rules do you consider?Note: There are 2 correct answers to this question.
- A. All key figure calculations have calculation inputs, which can be marked as stored or calculated.
- B. The calculation chain for a key figure must always result in a calculated key figure.
- C. Key figures can be calculated across different planning levels.
- D. Aggregation calculations using SUM or MAX functions must be based on a higher aggregation level.
Answer: A,C
NEW QUESTION 25
Which of the following are features of lag-based snapshots?Note: There are 2 correct answers to this question.
- A. Target key figures for these snapshots must have lag as a root attribute in its base planning level.
- B. The number of lag-based snapshots are limited to nine levels.
- C. Target key figures for these snapshots are exposed to the user in planning views.
- D. Lag-based snapshots are created in the Configuration app for a fixed time range.
Answer: A,D
NEW QUESTION 26
You are evaluating criteria for choosing the solver to support planning for a complex supply chain. What are some of the points that should be reviewed?Note: There are 2 correct answers to this question.
- A. Prioritization of demand elements one by one is achieved by unconstrained heuristics.
- B. Planning results can be generated faster by the optimizer.
- C. Push and Pull production models are used by the optimizer.
- D. Finite heuristics can achieve demand prioritization and pegging.
Answer: C,D
NEW QUESTION 27
Which conditions have to be fulfilled as a prerequisite to maintain a key figure disaggregation?Note: There are 2 correct answers to this question.
- A. The key figure is calculated and all editable.
- B. The key figure is stored and system editable.
- C. The key figure is stored and all editable.
- D. The key figure is calculated and system editable.
Answer: C
NEW QUESTION 28
Where can the results of a Time Series Analysis be used?Note: There are 2 correct answers to this question.
- A. In the Microsoft Excel add-in, where you can use them to limit and filter your planning views
- B. In Global (multi-stage) Inventory Optimization to calculate time-phased Recommended Safety Stock Outputs
- C. In the Manage Forecast Error Calculations app - Demand Planning app to calculate the Forecast Error CV
- D. During XYZ segmentation in the Manage ABC/XYZ Segmentation Rules app
Answer: B,D
NEW QUESTION 29
Which of the following conditions are relevant for subtotals in the planning view?Note: There are 2 correct answers to this question.
- A. Only attribute-based totals can be added to the planning view.
- B. The total value can be added before or after the selected attribute.
- C. The total number of attributes that can use subtotals in the planning view can be restricted.
- D. The values of the attribute-based total at the highest attribute level in the planning level can be changed.
Answer: B,C
NEW QUESTION 30
SAP IBP ensures interoperability with which applications?Note: There are 2 correct answers to this question.
- A. Financial Planning in SAP Analytics Cloud
- B. User management in SAP Success Factors
- C. Salesforce Sales Cloud
- D. Business Network in SAP Ariba
Answer: A,D
NEW QUESTION 31
......
SAP C-IBP-2208 Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
C-IBP-2208 Dumps PDF - C-IBP-2208 Real Exam Questions Answers: https://www.practicedump.com/C-IBP-2208_actualtests.html
Realistic C-IBP-2208 Dumps Latest Practice Tests Dumps: https://drive.google.com/open?id=1GsaT1NuJNCQz_lKx--tnSuXO-3vrO_Pt